CAR 2014 Compliance: When You Need a DOE Written Notification and Declaration
Introduction
Planning a new boiler, genset, scrubber or chimney? The Department of Environment (DOE) needs to hear from you twice: before you build, and after.
Under the Environmental Quality (Clean Air) Regulations 2014, known as CAR 2014, air emission sources come with two key submissions: the Written Notification (WN) and the Written Declaration (WD). Getting them right, and on time, is what keeps your project on schedule.
This guide explains what WN and WD are, when they apply, what each submission should contain, and the common mistakes that delay approval.
What is CAR 2014 and who does it apply to?
CAR 2014 is Malaysia's main regulation for controlling air emissions from industrial premises. It is made under the Environmental Quality Act 1974 and enforced by the DOE.
It applies to premises that operate air emission sources, such as:
- Fuel-burning equipment, including boilers, thermal oil heaters and generator sets
- Industrial processes that release dust, fumes, gases or vapours
- Air pollution control systems (APCS), such as scrubbers, bag filters and cyclones
- Chimneys and stacks that discharge to the atmosphere
CAR 2014 sets emission limit values and requires owners to notify DOE, design their systems properly, and prove they perform. WN and WD are the two submissions at the centre of that process.
Written Notification (WN): before you build
The Written Notification tells DOE what you plan to install before construction, installation or modification begins.
When a WN typically applies:
- Installing new fuel-burning equipment, such as a boiler, thermal oil heater or genset
- Installing a new air pollution control system
- Building a new chimney or modifying an existing one
- Changing a process in a way that alters emissions
What a WN typically includes:
- Process description and details of each emission source
- APCS and chimney design, with engineering calculations
- Predicted emissions compared with CAR 2014 limit values
- Drawings, site layout and supporting documents
A strong WN is built on sound engineering. Weak design calculations are one of the most common reasons submissions are returned.
Written Declaration (WD): after you build
The Written Declaration confirms to DOE that what was built matches the design, and that it actually performs.
A WD typically demonstrates four things:
|
What it shows |
Why it matters |
|---|---|
|
Built as designed |
As-built details match what was notified to DOE |
|
Performance proven |
Commissioning and emission testing show results within limits |
|
Ready to operate |
Sets the baseline for ongoing monitoring and DOE inspection |
|
Records in order |
Gives your EHS team documentation to show at any audit |
In short, the WN gets your project on record. The WD proves it is compliant in operation. You need both.
The right sequence: from study to declaration
Most delays happen when steps are taken out of order. Follow this sequence:
- Study: define the process, emission sources and the CAR 2014 limits that apply.
- Written Notification: submit the design and calculations to DOE before work starts.
- Build: install the equipment, APCS and chimney according to the notified design.
- Test: commission the system and carry out emission testing.
- Written Declaration: declare to DOE that the system is built as designed and performs within limits.
Planning the submissions early, at the design stage, is the simplest way to protect your project timeline.
Common mistakes that delay DOE approval
Late or weak submissions are costly. Watch out for these:
- Submitting the WN after installation has started. Equipment may be installed but unable to run while submissions are pending.
- Incomplete data or weak calculations. DOE may return the submission, sending you back to the start.
- An undersized APCS. If the system fails its emission test, you face expensive rework after installation.
- Changes made without updating DOE. As-built systems that differ from the notified design create problems at the WD stage.
- Treating the WD as an afterthought. Without a WD, your system is not shown to be compliant in operation, exposing you to enforcement action under the Environmental Quality Act 1974.
Why choose ESGPRO for your WN and WD submissions
ESGPRO Engineering & Consultancy designs, submits and validates until your submission is accepted. Our engineers have delivered 80+ DOE air-emission projects since 2015, as ZABSI Group's engineering division.
- Engineering-led: design calculations done right the first time.
- Submission to acceptance: we follow through with DOE, not just file.
- End-to-end: study, design, WN, testing and WD under one team.
- Backed by ZABSI Group: installation, maintenance and training under one roof.
Our DOE air-emission services include WN and WD under CAR 2014, APCS design, chimney design and registration, APCS performance monitoring systems and genset DOE approval.
Planning a new emission source? Talk to us first.
Website: www.esgpro.com.my Email: enquiry@esgpro.com.my
Frequently asked questions
What is the difference between WN and WD? The WN is submitted before construction, installation or modification, and tells DOE what you plan to build. The WD is submitted after installation, and confirms the system was built as designed and performs within limits.
Does a new genset need a DOE submission? Generator sets are fuel-burning equipment and may fall under CAR 2014. Check the requirements for your genset's capacity at the planning stage.
Can I start installation before submitting the WN? The WN should be submitted before work begins. Starting first risks delays and non-compliance.
Who prepares the WN and WD? Submissions are usually prepared by an engineering consultant with experience in air emission design and DOE requirements.
What happens if my system fails the emission test? The APCS will need to be rectified and retested before the WD can show compliance. Good design at the WN stage reduces this risk.
Do modifications to an existing chimney or APCS need a new submission? Modifications that change emissions or the notified design may need a new submission. Check with your consultant before making changes.
04 Nov 2026